HASiL’s construction industry FAQ explains that the timing of an e-Invoice for a construction progress claim depends on whether certification of the work done is required.
If certification is not required, the contractor must issue an e-Invoice in relation to the progress claim to substantiate the income generated.
If certification is required, the contractor may issue the e-Invoice upon obtaining the certificate of work done.
Contractors should therefore consider the certification requirements in their construction contracts when determining when to issue an e-Invoice for a progress claim.
建筑工程进度索款的电子发票处理
HASiL 建筑业常见问题解答说明,建筑工程进度索款的电子发票开具时点,取决于是否需要对已完成的工程进行认证。
若无需认证,承包商须就该进度索款开具电子发票,以证明所产生的收入。
若需要认证,承包商可在取得工程完成证明后开具电子发票。
因此,承包商应留意建筑合同中的认证要求,并据此确定进度索款电子发票的开具时点。